Turnkey Prefabricated Tubes
Turnkey custom prefabricated heat tubes delivered a week ahead of schedule.
Lorem ipsum sin dolor sit amet.
As part of the upgrade of a heater used for its coker unit, an Illinois-based oil and gas refinery needed to replace a large amount of deteriorating piping. Thanks to a long-standing partnership, the client once again tabbed Manhattan Mechanical Services to efficiently and effectively prefabricate 7,700 linear feet of heater tubes with return bends within a comparatively short timeframe. The results were a safe project, minimal downtime, increased quality and, ultimately, substantial cost-savings.
For this project, 7,700 linear feet of heat tubes, ranging from 3” and 4” in diameter, were fabricated at Manhattan Mechanical’s East Chicago, IN, facility to tolerances of 1/16 of an inch. The pipes were 100% X-ray-inspected for weld defects.
Permitting was required to move the 70-foot lengths of heater tubes to the client’s refinery. Manhattan Mechanical handled all aspects of this transport, including logistics equipment rental, the permitting required in multiple states, and driving the trucks.
Such a large pipe fabrication project demands finding the most efficient and effective way to deliver the product within a short time frame. The challenge lies in optimizing available space, planning when loads will be received and the timing of setting out the material, NDE (coordinating with subcontractors), and maintaining the capacity to work efficiently.
Thanks to the optimal organization and planning skills of Manhattan Mechanical’s multi-crafted professionals, all 7,700 linear feet arrived at the refinery a week ahead of the client’s schedule. As a result, the client saved a considerable amount on overall project costs.
Materials:
Pipe diameter: 3/4” to 30”
Wall thickness: .1875” to 8” .125 to schedule 160
NBIC “R” Stamp: B31.3 and API 1104
Tightest Tolerances: 5/32” gap +- 1/8”
In Process Testing/Inspection Performed: 100% X-ray and final PT
Standards Met:
Safety Procedures:
Capabilities Applied:
As part of the upgrade of a heater used for its coker unit, an Illinois-based oil and gas refinery needed to replace a large amount of deteriorating piping. Thanks to a long-standing partnership, the client once again tabbed Manhattan Mechanical Services to efficiently and effectively prefabricate 7,700 linear feet of heater tubes with return bends within a comparatively short timeframe. The results were a safe project, minimal downtime, increased quality and, ultimately, substantial cost-savings.
For this project, 7,700 linear feet of heat tubes, ranging from 3” and 4” in diameter, were fabricated at Manhattan Mechanical’s East Chicago, IN, facility to tolerances of 1/16 of an inch. The pipes were 100% X-ray-inspected for weld defects.
Permitting was required to move the 70-foot lengths of heater tubes to the client’s refinery. Manhattan Mechanical handled all aspects of this transport, including logistics equipment rental, the permitting required in multiple states, and driving the trucks.
Such a large pipe fabrication project demands finding the most efficient and effective way to deliver the product within a short time frame. The challenge lies in optimizing available space, planning when loads will be received and the timing of setting out the material, NDE (coordinating with subcontractors), and maintaining the capacity to work efficiently.
Thanks to the optimal organization and planning skills of Manhattan Mechanical’s multi-crafted professionals, all 7,700 linear feet arrived at the refinery a week ahead of the client’s schedule. As a result, the client saved a considerable amount on overall project costs.
Materials:
Pipe diameter: 3/4” to 30”
Wall thickness: .1875” to 8” .125 to schedule 160
NBIC “R” Stamp: B31.3 and API 1104
Tightest Tolerances: 5/32” gap +- 1/8”
In Process Testing/Inspection Performed: 100% X-ray and final PT
Standards Met:
Safety Procedures:
Capabilities Applied: